Overall Summary: 
The Electricity (Capacity) Supply and Consumption Rules regulate the relationships, between the Distribution licensee, low-capacity power plant, on the one hand, and consumer, on the other, in the process of electricity purchase, sale, distribution, pass through and/or consumption. In particuar, they introduce micro-generation and avoided-cost-based net-metering.
Access
Energy access priorities: 
Electricity Distribution licensee is obliged to provide consumer with safe, uninterruptable and reliable electricity supply within relevant parameters, in accordance with the obligations under the legislation, license terms, these Rules and corresponding agreement.
Energy access action plan: 
Distribution licensee is obliged to: a. provide service to all types of the consumer in accordance with these Rules; b. follow established technical and safety standards and rules; c. provide constant service for the consumers – among them, permanent 24 hour telephone hot-line service; d. carry out immediate response to the notification about termination of electricity supply or/and to the voltage deviation from the established norms; e. sell electricity to the retail consumer (according to the terms established in these Rules); [...].
Renewable Energy
Net metering: 
The retail consumer is authorized to connect his own low-capacity power plant (the design capacity of which does not exceed 100 kW) to the Distribution licensee free of charge and carry out supply of electricity produced by him under current legislation and defined terms under these Rules. The Distribution licensee is obliged to support the connection to the distribution network of any power plant and communicate with electricity producers under the legislation and defined terms under these Rules.---The retail consumer who owns a low-capacity power plant the design capacity of which does not exceed 100 kW is authorized to request the offset of electricity cost produced and supplied in the Distribution licensee’s network by him (after charging the retail consumer by the Distribution licensee under relevant rule) from the electricity cost received (consumed) from the distribution network, or/and refund the paid amount during the next settlement.
Mandatory connection: 
The retail consumer is authorized to connect his own low-capacity power plant (the design capacity of which does not exceed 100 kW) to the Distribution licensee free of charge and carry out supply of electricity produced by him under current legislation and defined terms under these Rules. The Distribution licensee is obliged to support the connection to the distribution network of any power plant and communicate with electricity producers under the legislation and defined terms under these Rules.
Pricing
Energy pricing: 
The cost of consumed electricity by the consumer is calculated on the basis of the individual electricity meter reading.---Billing and payment of consumed electricity shall be carried out on monthly basis (in accordance with consumed electricity by the retail consumer)
Investment
Independent power producers: 
Under Power Purchase Agreement the seller makes commitment to supply electricity according to the current legislation, these Rules and contractual obligations; and the buyer makes commitment to pay the cost for the received electricity and to follow the terms defined in current legislation, in these Rules and in the agreement.
Governance
Energy management principles: 
Under Power Purchase Agreement the seller makes commitment to supply electricity according to the current legislation, these Rules and contractual obligations; and the buyer makes commitment to pay the cost for the received electricity and to follow the terms defined in current legislation, in these Rules and in the agreement.