Meta Data
Title in national language: 
Программа освоения возобновляемых источников энергии и строительства малых гидроэлектростанций на 2016-2020 годы
Draft: 
No
Revision of previous policy?: 
No
Draft Year: 
2015
Effective Start Year: 
2016
Effective End Year: 
2020
Scope: 
National
Document Type: 
Programme
Economic Sector: 
Power
Energy Types: 
Power, Renewable, Hydropower
Issued by: 
The Government of the Republic of Tajikistan
Overall Summary: 
The Renewable Energy Development and Small Hydropower Plants Construction Program for 2016-2020 aims to increase the electric power supply to the population of remote and mountainous areas, increase the economic and energy efficiency of small power plants and create conditions for the operational maintenance of existing small power plants, their repair, as well as the possible production of equipment for the hydropower plant in Tajikistan.
Renewable Energy
RE priorities: 
17. In particular, the Program is aimed at improving the social situation of the population, the development of these regions, and the attractiveness of living in these areas by providing electricity and repairing equipment using renewable energy sources, [...]
RE action plans: 
18. This Program provides for a set of measures to solve the set tasks and develop small-scale energy in the Republic of Tajikistan, in the following areas: - construction of small hydroelectric power plants with working projects, feasibility studies and investors, scheduled for construction and commissioning, for the period 2016-2020; - construction of small hydroelectric power plants, for which there are feasibility studies for proposals to investors in 2016-2020; - construction of small hydroelectric power plants, on irrigation structures and watercourses, for which there are feasibility studies provided for proposals to investors for the period 2016-2020; - preparation of feasibility studies and working projects with the attraction of investments for the period 2016-2020, for the construction of small hydroelectric power plants; - installation of solar electrical installations on site, for which feasibility studies have been developed, with the attraction of investments for the period 2016-2020; - preparation of feasibility studies for wind installations, with the attraction of investments for the period 2016-2020.
Energy Supply and Infrastructure
Energy supply priorities: 
16. The goal of the Program is to increase the electricity supply to the population of remote and high mountainous regions, increase the economic and energy efficiency of commissioned small power plants and create conditions for the operational maintenance of existing small power plants, their repair, as well as the possible production of equipment for small HPPs in Tajikistan.