Title in national language: 
QUYẾT ĐỊNH VỀ CƠ CHẾ HỖ TRỢ PHÁT TRIỂN CÁC DỰ ÁN PHÁT ĐIỆN SỬ DỤNG CHẤT THẢI RẮN TẠI VIỆT NAM (Số: 31/2014/QĐ-TTg ngày 05 tháng 05 năm 2014)
Draft: 
No
Revision of previous policy?: 
No
Effective Start Year: 
2014
Scope: 
National
Document Type: 
Other
Economic Sector: 
Power
Energy Types: 
Power, Other
Issued by: 
The Prime Minister of the Socialist Republic of Vietnam
Overall Summary: 
The Prime Minister's Decision No. 31/2014/QD-TTg of 2014 on Support Mechanism for the Development of Power Generation Projects using Solid Waste in Vietnam regulates the support mechanism for the development of power generation projects using solid waste(s) in Vietnam.
Renewable Energy
RE prioritization, portfolio standards: 
Article 11. Responsibility for Power Purchase from Power Generation Projects Using Solid Waste(s)ю 1. The Purchaser shall be responsible for purchasing all electric power produced by the power generation plant using solid waste(s) under its jurisdiction. 2. The power purchase and selling shall be performed via the power purchase agreement, which is prepared in accordance with the MoITpromulgated Standardized Power Purchase Agreement applicable to power generation projects using solid waste(s). 3. The Purchaser shall be required, no later than 6 months from the issuance of the written request for electricity sale by the investor in power generation projects using solid waste(s), to sign the power purchase agreement with the Seller in accordance with regulations. 4. The duration of the power purchase agreement applicable to power generation projects using solid waste(s) is 20 years from the date of commercial operations. After 20 years, the two sides may choose to extend the existing agreement or sign a new agreement in accordance with existing legal regulations.
RE feed-in tariffs: 
Article 14. Electricity Price Support to Power Generation Projects using Solid Waste(s) 1. The Purchaser shall be responsible for purchasing all electric power produced by the power generation plant using solid waste(s) with the electricity purchase price (VAT exclusive) at the delivery point as follows: - For power generation projects using solid waste(s) that are directly incinerated, the price shall be VND 2,114/kWh (equivalent to 10.05 US cents/kWh). - For power generation projects using combusted gas collected from solid waste landfills, the price shall be VND 1,532/kWh (equivalent to 7.28 US cents/kWh).
RE capital subsidy, grant, or rebate: 
Article 12. Preferences for Investment Capital and Taxes. 1. Mobilization of investment capital a) Investors shall be permitted to mobilize capital from domestic and foreign organizations/individuals for the purpose of investing in the implementation of power generation projects using solid waste(s) under the provisions of existing laws on investment. b) Power generation projects using solid waste(s) shall be entitled to preferential treatment on investment credits as prescribed in current regulations on State investment and export credits.
RE reductions in taxes: 
Article 12. Preferences for Investment Capital and Taxes. [...] 2. Import duties: Power generation projects using solid wastes shall be exempt from import duties for goods imported to establish project fixed assets; goods imported as raw materials, materials and semi-finished products that are not domestically produced and imported for project’s production purposes under the provisions of the existing laws on import and export taxes. 3. Corporate income tax: The exemption and reduction of corporate income tax applicable to power generation projects using solid waste(s) shall be similar to that of projects included in preferential treatment categories as prescribed in the current legal regulations on taxes. Article 13. Preferences for Land. 1. Power generation projects using solid waste(s), and transmission line and transformer station projects for connection to the national electricity grid shall be entitled to the exemption/reduction of land use/rental costs as prescribed in the existing laws applicable to projects included in preferential treatment categories. 2. On the basis of the plan approved by the competent authority, the Provincial People's Committee shall be responsible for allocating adequate land for the investor’s implementation of power generation project(s) using solid waste(s). The compensation and support to premise clearance shall comply with the provisions of existing laws on land.