Public competitive bidding/tendering:
The implementation mechanism for selection of potential developers under LSS programme shall be through a Competitive Bidding framework, unless otherwise directed by the Minister.---Capacity for Bid: The target capacity for the LSS program is 1000 MWac by 2020 with annual capacity capped at 200MW ac for Peninsular and 50MWac for Sabah for 2017, 2018, 2019 and 2020.---The Power Purchase Agreement (PPA) shall be based on take and pay, energy only under Build, Own and Operate (BOO) concession;---The solar rate offered by the bidder shall be site specific. The LSS power plant may include combine plants from several different sites and if all the facility is connected to one nodal point, then a single PPA shall be used;---The LSS that is allowed to be connected to the Transmission Network shall be of the capacity of
30MWac to 50MWac via one Interconnection Point.